Rohit Chawla & Ors vs. M/s. Bombay Dyeing & Mfg. Co. Ltd, Decided on 31/12/2019
Consumers of the project ought to be compensated
by the builder for undue delay in project even if the agreement for sale is
executed prior to RERA.
Facts of the case:
Bombay Dyeing (the “Promoterâ€) launched a luxurious project
named as “Island City Center†at Spring Mills Compound, Wadala, before the
enactment of RERA. The Promoter in its detailed advertisement while booking
promised numerous facilities and the due date of possession was taken as 2017.
On the basis of the representations and assurances of Promoter,
Allottees had agreed to purchase flats from Phase-II of the project which
consisted of two towers i.e “ICC Tower One†and “ICC Tower Twoâ€. Promoter had
accordingly issued allotment letters wherein a list of amenities to be provided
in the said unit were separately attached.
The flats were allotted to the Allottees under subvention scheme
in which 80% of consideration was to be paid by the Allottee at the time of the
possession. The Allottees had already paid 19% of the consideration to the
Promoter in the year 2012-2013.
When RERA was enacted, the construction status of the said
project was far from completion. Therefore, the Promoter unilaterally changed
the date of completion of the project to 31.08.2019 while registering the
project under RERA.
The Allottee found that there is no facility provided in the
project as promised while booking. Hence they filed a complaint with MahaRERA
Authority for cancellation of allotment letters and for refund of entire amount
paid by them along with interest and compensation under section 18 for breach
of agreement.
Order passed by
MahaRERA Authority:
The MahaRERA Authority
did not agree with complainants and directed the Promoter to execute and
register agreement for sale as per section 13 of the Act within 30 days. It
directed that if the Allottee intent to withdraw from the project then such
withdrawal would be guided by the terms and conditions of the allotment
letters. No order was passed for interest and compensation sought by the
Allottee.
Aggrieved by the said
order of the Authority, the Allottee
filed appeal before the Maharashtra RERA Appellate Tribunal.
Issue before Appellate Tribunal:
1. Whether Section 12 of RERA applies prospectively or
retrospectively or retroactively?
2. Whether Promoter committed breach of Section 12 of RERA Act?
3. Whether Allottee are entitled for refund along with interest and
compensation from the Promoter under Section 18? if yes, then what will be rate
of interest?
Allottees’ contentions:
They
urged that:
1. Section 12 and Section 18 of RERA Act are made
applicable retroactively as RERA is social and beneficial legislation.
2. Even if the transaction had taken place prior
to enactment of RERA, provisions of RERA regarding compensation including
section 12 and section 18 will apply to such transaction.
Promoter’s contentions:
The
Promoter opposed the Complainants appeal stating:
1. Retroactivity will not affect any rights that
have already accrued before the Act came into force else it will impose new
liability which did not exist before such enactment.
2. Reliance
was placed in the case of G.J Raja
vs Tejraj Surana[1]
and CIT-A New Delhi vs Vatika
Township Pvt Ltd[2]
to hold that amendment apply only to offence giving rise to case after 2018
and it cannot be applied retrospectively.
3. Reliance was also placed on the case of Hitendra Vishnu Thakur vs State of
Maharashtra[3],
to hold that a statute which not only changes the procedure but also creates
new rights and liabilities shall be construed to be prospective in operation
unless otherwise provided either expressly or by necessary implication.
4. It urged on the remanding the matter to
Authority as they did not get opportunity to contest the matter on merit for
deciding the complaints under section 12 and 18 of Act.
Key Principles:
1.
Allottee entitled to cancel the booking where the developer has delayed
the possession.
2.
Section 18 compensates an allottee for depriving him of the use of the
funds paid by him. Hence, interest is imperative.
Verdict of Appellate Tribunal:
The Appellate
Tribunal granted relief to the aggrieved Allottee and ruled that since the
project is registered under section 3 of the Act, the Promoter is governed by
the provisions of RERA. It observed that:
(i)
As
per the principles laid down in the case of Neelkamal
Realtors Suburban Pvt. Ltd vs Union of
India[1]
a promoter is not absolved of the liability under the agreement for sale.
Section 12 and 18 of RERA is compensatory and is retroactively applicable. It
pointed out Interest is not penalty.
(ii) On the question of remanding the matter it
stated that opportunity of hearing was given to both the sides and thus there
is no requirement of remanding the matter.
(iii) On the question of breach of section 18 by the
Promoter, Tribunal placed reliance upon the case of Fortune Infrastructure vs Travor Dlima[2],
to hold that when no date of possession is mentioned in the agreement the
promoter is expected to hand over the possession within reasonable time and the
period of 3 years is held to be reasonable time. Thus the Promoter herein
committed breach of section 18 by failing to give the possession in the year
2017.
(iv)On breach of section 12 by the Promoter,
Tribunal stated that ample documentary evidence on records shows that the
Promoter has failed to keep up with his commitments and therefore committed
breach of section 12. Thus entitling the Allottees to withdraw from the project
and to claim refund alongwith interest from the Promoter.
(v) On the
status of Occupation certificate reliance was placed in the case of Pioneer Urban Land Vs. Govindan Raghvan[3]
to hold that once the builder fails to fulfil the obligation of obtaining
Occupation certificate and offering possession of flat within the time as
stipulated in the agreement, the buyer could not be compelled to take
possession of the flat when it was offered almost 2 years after grace period
under agreement expired.
On
Acelegal Analysis:
This decision of Appellate Tribunal is in line with the Neelkamal’s
case of the Mumbai High Court. It upholds retrospective applicability of
section 18 while upholding eligibility of interest. The tribunal has refused to
accept the distinction raised by the Developer that the cause of action arose
before enactment of RERA and hence remedy under RERA was not available on that
date. This is an important decision to that extent.
However, this decision has tilted the pendulum to the other extreme.
The buyers who feel that the property prices have come down in the current
market conditions will queue up for cancellation of their allotment and seek
refund with interest. Law is dynamic and should be applied considering the
market conditions and state of economy. If the builders face cancellations
where will they get money to repay the buyers. The money collected, if applied
in the project will not be available. Secondly, it raises another question. From
what date the interest is payable. Will the buyer be paid interest for the
period during he had the title of flat in its name? The request of the buyers
for refund will sabotage the project creating more issues for continuing buyers.
Don't throw the baby out with the bathwater.
Disclaimer :
This information Memorandum is meant solely for the
purpose of information. Acelegal do not take any responsibility of decision
taken by any person based on the information provided through this memorandum. Please obtain professional advice before relying on
this information memorandum for any actual transaction. Without prior permission of Acelegal,
this memorandum may not be quoted in whole or in part or otherwise referred to in any document.