South East Asia Marine Engineering and Constructions Ltd (SEAMEC Ltd) vs. Oil India Limited; Civil Appeal no. 673 of 2012 (SC)
On a conjoint reading of various clauses in the
contract it was held that the parties did not contract for increase in the
contract value due to increase in the cost of input for reasons strictly other
than amendment to the law.
Facts of the case:
SEAMEC Ltd
was awarded a work order pursuant to a tender floated by OIL for the purpose of
well drilling and other auxiliary operations in Assam. The contract was
extended for 2 successive periods of one year each and the contract expired on
04.10.2000.
During the subsistence of the contract, the prices of High Speed
Diesel (HSD) increased. SEAMEC Ltd raised a claim that increase in the price of
HSD triggered the “change in law†clause 23.3 under the contract and claimed reimbursement.
When OIL rejected the claim, SEAMEC Ltd invoked the arbitration clause
referring the dispute to an Arbitral Tribunal comprising of three arbitrators.
Award of
Arbitral Tribunal
Tribunal applied the rule of construction while interpreting the
clause 23.3 of the agreement which it termed as “Habendum clauseâ€. It held that
the increase in the operational cost due to enhanced price of the diesel
through a “circular†though not a “law†in literal sense but has a “force of
law†and thus falls within the ambit of clause of the agreement and allowed the
claim to SEAMEC Ltd. Aggrieved, OIL challenged the order under section 34 of
Arbitration Act before a District Judge.
The District Judge upheld the award. The order was challenged
before the High Court.
Order of the
High Court
The High Court interpreted that 23.3 was not inserted for revising a fixed rate of contract. It held that clause 23 of the contract is akin to the “force majeure clause†and is pari materia to the ‘doctrine of frustration and supervening impossibility’. It thus set aside the award observing that it was passed overlooking the terms and conditions of the contract. Aggrieved, SEAMEC Ltd filed appeal before the Supreme Court.
Issue before Supreme Court:
1. Whether the interpretation provided to the contract in the award
of the Tribunal was so unreasonable and unfair that it required interference
under section 34 of the Arbitration Act?
2. Whether SEAMEC Ltd. was entitled to claim reimbursement of the increased cost of input on consideration of the contractual clauses?
Key Principles:
1. Habendum clause is a part of the agreement which defines the extent of interest being granted and any conditions affecting this grant.
2. A written contract must be read as a whole.
3. Award cannot be passed de hors the contract between the parties.
The
Supreme Court did not subscribe to the reasons provided either by the Tribunal
or the High Court. However, it rejected the claim of reimbursement by SEAMEC
and made the following observations:
(i)
On
a conjoint reading of various clauses of contract it was clear that it is based
on a fixed rate. The parties mitigated the risk of increase in price before
entering into the contract. Thus a price fluctuation cannot be brought under
clause 23 of contract unless the language of the contract points to the
inclusion.
(ii) The contract has recognized force majeure
events and the parties had agreed for payment of force majeure rate to tide
over any force majeure event.
(iii) Thus any price fluctuations in essential
element required for completion of contractual obligation or full and proper
sustenance cannot be considered as change due to ‘subsequent change in law’
clause, even if such a change arose by a government order.
(iv)If a clause stipulates a pre-determined rate
on occurrence of force majeure event to support a temporary event, it cannot be
considered as a case to be viewed as a Force Majeure event unless it is
specifically articulated in the contract to that effect.
(v) The award having been passed dehors the
contract entered between the parties, the provisions of section 34 of the Arbitration
Act was righly invoked. It was not a review or appeal against the award but the
award was seriously incorrect that it required interference of the court.
Acelegal Analysis:
(i)
The
consequences of a force majeure event has been codified in section 56 of the
Indian Contract Act. The parties have to contract as to what they consider as a
force majeure event. Section 32 of the Indian Contract Act lay down when the
obligation of a party can be excused. However, both these provisions in statute
cannot be applied in isolation without first determining from the complete
reading of contract as to what are the events that the parties have decided to
treat as Force Majeure and its consequences.
(ii) The Courts in India, while interpreting the
force majeure clause are applying strict rules of interpretation and hence not
ready to hold that an agreement is void or frustrated on the basis of indirect
application of a situation. The courts are not inclined to invoke section 56 of
the Contract Act, in a light hearted manner and nor is there any need to do so.
The questions of increase in cost for a provider is his business risk and it
cannot be used to either to wriggle out of the contractual obligations or to
claim additional consideration over and above the contract price decided and
determined after due negotiation between the parties unless specifically
covered. There are no assumptions made as to the inclusion
of any event unless specifically mentioned under the contract.
This information Memorandum
is meant solely for the purpose of information. Acelegal do not take any
responsibility of decision taken by any person based on the information
provided through this memorandum. Please obtain professional advice before relying on
this information memorandum for any actual transaction. Without prior permission of Acelegal,
this memorandum may not be quoted in whole or in part or otherwise referred to in any documents.